Rack Power Check Open the tool

PDU load calculator, with one side off

A rack on two PDUs, each on its own feed. Enter the rack's draw and each PDU's rating to see what each carries now, and what the other carries when one goes off, against its rating and your limit.

The rack and its two PDUs

Filled in with example numbers. Change any of them.

What each PDU carries

The figures appear here when the page has loaded.

Estimates only, from the numbers you enter. Single-phase 230 V. The rack is one load here: banks and breakers inside each PDU are not checked.

Check the whole room

In the full tool each device is plugged into a real outlet and bank, so it can show which bank trips first and which devices go dark, step by step. The load typed here goes with it, as two PDUs on two feeds. The room open in the tool is kept, unless it came from here unchanged. Its "Bring back the last room" button restores it. Only one earlier room is kept.

Why the survivor matters

With two PDUs sharing a load, losing one means the other carries all of it. If each side normally carries more than half of the limit, the survivor starts above the limit. With an 80 % limit that is 40 % on each side, which is why 40 % is a common target for a two-feed rack.

How the share is worked out

The share is the part of the draw that sits on PDU A while both are on. When a PDU goes off, its part moves to the other one, as it does when a device's two power supplies share its load. A device with one supply would go dark instead; the full tool handles that device by device.

Where this calculator stops

It treats the rack as one load on two PDUs. It does not know which device is plugged into which bank. A bank behind a breaker smaller than the PDU's rating can trip first, and that is what the full tool shows.

What is not seen

Whether the two feeds really are separate is not checked: two PDUs on the same circuit or the same UPS both go off together. Nothing upstream of the feeds is modelled.

Questions

What if the load is not shared equally?

Change the share. A device whose second supply stands by puts its whole draw on one side; the full tool lets you set that for each device.

Is 40 % a rule?

No. It is what an 80 % limit gives when two sides share equally. Both numbers are settings.

Does it account for the UPS or the supply upstream?

No. It does not see what is upstream of the feeds.

Does it check breaker banks?

Not here. The full tool checks every bank.

What does "expected to trip" mean?

The load is above the rating you entered. It is an estimate from your numbers, not a prediction of what the equipment will do.